MERCES BUILDERS SDN. BHD. vs DEMIRAMA SDN. BHD (MJLR 2009b4) Clement Skinner, 29/1/2009, SS

-1- [CSK.22-141-2002-II]

5 MALAYSIA

IN THE HIGH COURT IN SABAH AND SARAWAK

AT KOTA KINABALU

CIVIL SUIT NO. K22-141 OF 2002-II

BETWEEN

10 MERCES BUILDERS SDN. BHD. … APPELLANT/DEFENDANT

(Company No.: 175572-A)

Lot 1-1-17, Api-Api Centre

88300, KOTA KINABALU

SABAH

15 AGAINST

DEMIRAMA SDN. BHD. … RESPONDENT/PLAINTIFF

(Company No.: 437805-M)

Suite 2.55, 2nd Floor, Block C

Kompleks Karamunsing

20 KOTA KINABALU, SABAH

BEFORE THE HONOURABLE JUSTICE

DATUK CLEMENT SKINNER IN CHAMBERS

25 JUDGMENT

This is the hearing of an appeal to the Judge in Chambers

against the decision of the Deputy Registrar given on 02.05.2003.

On that day summary judgment was granted in the sum of

30 RM500,000.00 against the defendant under Ord. 14 Rules of the

High Court 1980 (‘the RHC’).



-2- [CSK.22-141-2002-II]

5 The defendant was awarded a contract by the government to

repair and upgrade the Likas Sport Complex at Kota Kinabalu

(‘the contract works’) valued at some RM113.2 million. The

defendant then engaged the plaintiff as a “Management Contractor”

to undertake the contract works. An Agreement (‘the agreement’)

10 was entered into between the plaintiff and defendant for that purpose.

One of the terms of the agreement i.e. Clause 5.1 states that

the plaintiff shall covenant and undertake that upon the request of the

defendant, the plaintiff shall provide or cause to be provided to and /

15 or for the benefit of the defendant as the main contractor, a corporate

guarantee or any other form of security as shall be required to enable

the defendant to provide or obtain a Performance Bond in the sum of

RM5,660,189.62 in favour of the government in respect of the

contract works awarded to the defendant.

20

This suit was commenced by the plaintiff against the defendant

for the repayment of a loan of RM500,000.00 which was payable on

demand, which it had granted to the defendant pursuant to an oral

agreement made on or about 02.04.2001 between the parties. Full

25 particulars were given of the amount paid to the defendant by way of

loan, namely, the payment on 02.04.2001 of RM500,000.00 into the

defendant’s bank account no.: 21002800109910 at RHB Bank,

No. 81 – 83, Gaya Street, Kota Kinabalu, Sabah. The plaintiff alleged

that despite a demand for repayment of the loan, the defendant had

30 refused to pay the same. Hence this suit.



-3- [CSK.22-141-2002-II]

5 The defendant filed a defence and counter-claim. It is the

defendant’s case that the RM500,000.00 it received from the plaintiff

was not a loan as alleged but instead the sum was a part payment

made by the plaintiff towards its obligations under Clause 5.1 of the

agreement, to enable the defendant to furnish the Performance Bond

10 to the government.

The defendant also alleged that the plaintiff had committed a

breach of the agreement, in that, the plaintiff had failed to pay the

balance of the amount under Clause 5.1 and had supplied piling

15 materials which did not comply with the specifications in the

agreement. Hence the defendant’s counter-claim for damages for

breach of the agreement against the plaintiff.

After the defence was filed the plaintiff filed its application for

20 summary judgment.

It is the defendant’s case that summary judgment should not

have been entered against it as:

(a) the question whether the RM500,000.00 it had received

25 from the plaintiff was a loan or whether it was only a part

payment under Clause 5.1 so as to enable the defendant

to furnish the Performance Bond, is a matter which gives

rise to a serious issue to be tried. It needs to be further

investigated. It is not suitable for summary disposal;

30 (b) there ought for some other reasons to be a trial of the

plaintiff’s claim;



-4- [CSK.22-141-2002-II]

5 (c) a dispute has arisen between the parties on the

interpretation of Clause 4.1 of the agreement as to

whether the plaintiff was engaged to manage the contract

works or was engaged to carry out those works;

(d) there was delay on the part of the plaintiff in applying for

10 summary judgment.

The law on the matter at hand is set out in National Company

for Foreign Trade v Kayu Raya Sdn. Bhd. [1984] 2 MLJ 300 where

the Federal Court held that once the plaintiff satisfies the

15 requirements under Ord. 14 i.e.;

(i) that the defendant has entered an appearance;

(ii) the statement of claim must have been served on the

defendant; and

(iii) the affidavit in support of the application complies with the

20 requirements of rule 2 of Ord. 14;

the plaintiff has established a prima facie case and becomes

entitled to judgment. The burden shifts to the defendant to

satisfy the Court why judgment should not be given against it.

25 I am satisfied that the plaintiff’s application here has satisfied all

the requirements stated in the case of National Company for Foreign

Trade, and that the plaintiff has established a prima facie case for

summary judgment against the defendant. The burden has shifted to

the defendant to show cause why judgment should not be given

30 against it.



-5- [CSK.22-141-2002-II]

5 As I mentioned earlier, it is the defendant’s case that it has

discharged that burden by showing that the issues raised by it in

(a), (b), (c) and (d) above all give rise to bona fide serious issues

which require to be tried.

10 I will now consider each of these issues to see whether they do

give rise to any triable issues.

(a) Was the RM500,000.00 a part payment under Clause 5.1

and not a loan?

15

I find that the defendant’s assertion that the RM500,000.00 was

a part payment only under Clause 5.1 of the agreement does not

stand up to closer curial scrutiny for the following reasons.

First, Clause 5.1 expressly states that the obligation of the plaintiff to

20 provide security to the defendant so that the defendant may in turn

furnish a Performance Bond to the government, only arises

“upon the request” of the defendant. The parties to a contract are

bound by the terms they have agreed to. To enable the defendant to

maintain its assertion that the RM500,000.00 was a part payment of

25 the security mentioned in Clause 5.1, the defendant must first state

the facts on which such an assertion can be based. The defendant

must at least show that it had requested the plaintiff to provide the

security and that explains the payment of the RM500,000.00 to it, but

the defendant has not placed any evidence before the Court of such

30 request. The defendant has submitted that the Court should allow it

to amend its pleadings, to enable it to plead particulars of such



5 request. I find no merit in this submission because the defendant

need not apply for an amendment before it can raise such assertion

because it has had an opportunity to file affidavits to oppose the

plaintiff’s application and could easily have stated in its affidavits the

date, time, place and mode of such request, if any. The fact that the

10 defendant did not do so is consistent with such a request not being

made. Second, Clause 15.1 of the agreement states that any notice

or demand or other communications required to be given or made

under the agreement shall be in writing. So, any request which the

defendant made pursuant to Clause 5.1 must have been made in

15 writing. The defendant would surely be in possession of a copy of its

written request if one was made to the plaintiff. The fact that the

defendant has not been able to produce such a written request is

consistent with the fact that no such request was ever made.

20 Accordingly, the defendant’s assertion that the RM500,000.00

was a part payment of the security mentioned in Clause 5.1 is

inconsistent with the undisputed contemporaneous documents in the

case.

25 (b) There ought to be a trial ³for some other reasons´?

The defendant says that there ought to be a trial for some other

reasons, namely, the plaintiff is alleged to be in breach of the

agreement for which the defendant has filed a counter-claim. I do not

30 agree with this contention. In so far as it is alleged that the plaintiff is

in breach of Clause 5.1 because it did not pay the full amount of the



-7- [CSK.22-141-2002-II]

5 security for the Performance Bond, the defendant’s allegation will

only be capable of raising an issue to be tried if the defendant can

point to some facts which show that it had made a request to the

plaintiff to be furnished with the security. Unless the defendant can

do so, of which there is none before the Court, its allegation of breach

10 of Clause 5.1 by the plaintiff is a complete non-starter. The

defendant’s counter-claim being based on the plaintiff’s alleged

breach of Clause 5.1 it is likewise a non-starter.

(c) Alleged difference in interpretation of Clause 4.1.

15

In my judgment, whether the correct interpretation of Clause 4.1

of the agreement mean that the plaintiff was appointed as a

“Management Contractor” or only the contractor to undertake the

contract works, is completely irrelevant to the issue whether the

20 RM500,000.00 was a loan from the plaintiff to the defendant or the

sum represented a part payment under Clause 5.1. It does not give

rise to any bona fide triable issue as far as the latter question is

concerned.

25 Was there delay in applying?

According to the defendant, the plaintiff had delayed in filing its

application until after the defence in this action was filed. According

to the defendant, that delay was fatal to the plaintiff’s application for

30 summary judgment. In support the case of Krishnamurthy & Anor v

Malayan Finance Corporation Bhd. [1986] 2 MLJ 134 was cited. I do



-8- [CSK.22-141-2002-II]

5 not agree. Delay per se in making the application will not defeat the

plaintiff’s application for summary judgment where no bona fide

triable issues exist. See Perkapalan Sharmelin Jaya Sdn. Bhd. &

Anor v Alpine Bank Transport New York [1997] 3 MLJ 818.

10 In the result for all the reasons given above, I find that no bona

fide triable issues have arisen that requires to be tried. The

defendant has not discharged the burden on it of showing why

summary judgment should not be entered against it.

15 I accordingly dismiss the defendant’s appeal with costs and

affirm the Order made by the learned Deputy Registrar.

20

25

DATUK CLEMENT SKINNER

Judge

30 Date : 29th January 2009



-9- [CSK.22-141-2002-II]

5 Counsel

For Appellant / Defendant : Cik Munirah Bashir Khan

Messrs. Angela Ubu & Associates

KOTA KINABALU

10

For Respondent / Plaintiff : Mr. Chong Kian Ming

Messrs. Kianming & Associates

KOTA KINABALU