WIRA CENTRAL (M) SDN BHD v REGAL MERGER SDN BHD (MJLR2009a16) Zabariah Yusof,Malaya

1

DALAM MAHKAMAH TINGGI MALAYA DI KUALA LUMPUR

(BAHAGIAN SIVIL)

GUAMAN SIVIL NO: S5-22-222-2008

ANTARA

WIRA CENTRAL (M) SDN BHD ………..…PLAINTIF

DAN

REGAL MERGER SDN BHD …………DEFENDANT

GROUNDS OF JUDGMENT

Enclosure 7 is an application by the Plaintiff for Summary Judgment

under 14 RHC against the defendant.

Brief Facts;

The Defendant was undertaking the development of a project known

as "Cadangan Pembangunan Kedai Pejabat 3 Tingkat seblk 30 unit

di atas PT 83, Bandar Bukit Baru, Seksyen IV, Daerah Melaka

Tengah, Me/aka" ("Project") and had engaged the Plaintiff as the

contractor cum project manager for the said Project.

2

Regional Development Consortium Architect was the Superintending

Officer/Architect ("Architect") appointed by the Defendant.

The terms and conditions of the Plaintiff's said engagement included,

inter alia, the Pertubuhan Arkitek Malaysia "Agreement and

Conditions of Building Contract" (Private Edition without Quantities)

[1998 Edition1 ("PAM Conditions of Contract").

The Plaintiff had commenced work on the said Project pursuant to its

said engagement.

Subsequently and as evidenced by the Defendant’s letter dated

19.7.2006, the Defendant assumed possession and responsibility for

the said Project from the Plaintiff and thereby terminating the

Plaintiff's said engagement as contractor of the said Project.

Consequently and following valuation undertaken by the said

Quantity Surveyor, the Architect issued a certificate certifying a sum

of RM905,480.49 (Certificate) being the amount due and owing by the

Defendant to the Plaintiff for works done and materials supplied.

The said Certificate also confirmed that a sum of RM 335,312.84 had

been deducted and was being held by the Defendant as retention

sum.

Despite requests/demands from the Plaintiff, the Defendant had failed

to pay to the Plaintiff the above sums. As such, the Plaintiff had on

22.2.2008 commenced a writ action against the Defendant to claim

the said sum of RM 905,480.49 and the Retention Sum of

RM335,312.84.

3

The Plaintiff's claim against the Defendant is for works done and

materials supplied in relation to the Project before the termination of

the Plaintiff's engagement as contractor on/about 19.7.2006.

The Plaintiff states that it is entitled to the payment of the said sum of

RM 905,480.49 and the Retention Sum of RM 335,312.84 on the

following reasons:

a) given that the Certificate issued by the Architect was a final

valuation of the works done by the Plaintiff, this Certificate is proof

that the sum of RM 905.480.49 is undisputedly due from the

Defendant to the Plaintiff;

b) pursuant to Clause 30.2 of the PAM Conditions of Contract, once

the said Certificate is issued by the Architect the contractor

(Plaintiff) is entitled to payment within 30 days. .

c) As the Defendant had failed to make such payments to the

Plaintiff within the 30 days (i.e on/before 30.12.2007), the said

sum of RM 905,480.49 ,or becomes due and payable to the

Plaintiff;

d) further, as at the date of filing of the Summons, the Defendant

has not raised any complaints or evidence to show that the

certified sum of RM 905,480.49 was erroneous by reason of

fraud, dishonesty or fraudulent concealment of the works done or

that the Defendant has a cross claim alleging defective work.

4

Additionally, the Plaintiff states that taking into account the

termination of the Plaintiff's engagement in/around 19.7.2006 and the

fact that the Defendant had failed to raise any complaints of defective

work (which would allow the Defendant to make deductions from the

Retention Sum), the Retention Sum of RM 335,312.84 is also due

and payable to the Plaintiff.

The Court’s Findings:

The Plaintiff have agreed to terminate the PAM Conditions of

Contract by a letter dated 29.5.2006 and substitute it with a new

contract where the parties have agreed to the new terms inter alia as

follows:

a) The plaintiff will surrender the whole project inclusive of the

current on going 30 units shop office to the Defendant;

b) A final account shall be carried out and payment terms of such

due outstanding owing shall be arranged and agreed;

c) upon receiving the final account, both parties shall discuss the

matter for final agreement and formulate the method of

payment;

d) the outstanding sum agreed and accepted between both

parties shall be honoured within 14 days from the date of

signing of agreement for acceptance of final account of the

project.

5

Therefore triable issue arises as to whether on the terms and

conditions of the new agreement, all the obligations of the parties

have been fulfilled, bearing in mind that the PAM Contract is no

longer in existence.

This issue of the PAM contract has been terminated and new terms

and conditions being emplaced have not been disclosed in the

Statement of Claim and neither in the affidavit of the Plaintiff. (Refer

to the case of Affin Bank Bhd v Datuk Ahmad Zahid Hamidi [2005] 1

CLJ 521). The matters as stated in paragraphs (b) to (d) above are

issues to be tried.

Moreover, earlier a finding has been made on the issue that there are

issues to be tried, by the Judge hearing the application for an

injunction in Enclosure 4. Therefore I am estopped from deciding on

the same issue.

Therefore, base on the above reasoning the claim by the Plaintiff for

summary judgment under 0 14 RHC is dismissed with costs.

Datin Zabariah Mohd Yusof

Tarikh 10.7.2009

Bagi Pihak Plaintiff : Encik Micheal Chow

Tetuan Micheal Chow.

Bagi Pihak Defendant : Encik Haresh Mahaderan

Tetuan Haresh Mahadevan & Co.

6

7